Work gets underway

Tuesday, 23 April, 2013 (All day)

Not much sign of change on the front of the Hall, but note the logos of the key funders. However, the inside has now been totally stripped out and all the flooring removed. And lots going on in the  car park area now. This is associated with moving the main electricity cables which run out from the sub-station, and some drainage works. The electricity cable rerouting will also involve digging up the road in front of Smithy Cottage, scheduled to start on or soon after 8 May. The work should take only a few days and does not involve any road closures.

Slates removed from the roof will be retained and replaced as much as possible.