More floors and walls

Monday, 12 August, 2013 - 11:30

Floors for the rooms on the outside of the main hall have been filled in with gravel and flattened down, and the toilets and plant room floors have now been concreted.


There has also been progress with wall building, both outside (where the new coffee shop will be) and inside, in the former meeting room.